Close to $1M needed to finish bike trail in Middletown
No city money spent on recent GMR Bike Trail leg; last portion could be costly.
By Michael D. Pitman, Staff Writer Updated 10:26 PM Saturday, June 2, 2012
MIDDLETOWN — The city will need close to $1 million in order to complete the final portion of the Great Miami River Bike Trail within the city. Officials with bike trail contractor Barry Brown Paving are checking off the final items on the punch list for the 1.2-mile stretch recently completed. The city now has about 9 miles of bike trails, and bikers and walkers can travel from Oxford State Road to close to North Breiel Boulevard Road. But the last nearly 2 miles of the trail — which will end at Baxter Drive in Franklin — will be costly. About $900,000 will be needed to construct that portion, but 55 percent of that cost is for about 1,000 feet of retaining walls, Rob Nichols, an engineer with the city’s Public Works and Utilities Department. “There’s not a whole lot of land and it would require a retaining wall,” said Nichols, “so it is more expensive.” Once that stretch is finished, bike riders will be able to travel to near Piqua on the trail. City Manager Judy Gilleland said while quality of life amenities like the bike trail are an important aspect to the Middletown community, its’s not a top priority. “The bike path has been built over many, many years as grant funds became available. There has not been a guarantee that it would ever be complete but it’s a project we keep in the back of our minds if the funds become available,” she said. Gilleland said the city relies on funding it cannot use for essential city services, such as emergency services or maintenance of the streets. Only funds are earmarked for recreation trails or park-related activities would be used, she said. There are some initial discussions with regional organizations about funding options and resources. No city money was spent completing this recent leg of the trail. The bulk of the funding for this most recent portion — which cost $501,000 — came from an Energy Efficiency and Conservation Block Grant from the federal stimulus package. The remaining money came from the Middletown Community Foundation and the Miami Conservancy District. The project was to be completed this past fall, Nichols said, but the schedule was compromised due to delays with the contractor and environmental red tape with approvals from the Ohio Department of Transportation.
|
|
Vivian Moon
MUSA Council
Joined: May 16 2008
Location: Middletown, Ohi
Status: Offline
Points: 4187
|
Post Options
Thanks(0)
Quote Reply
Posted: Jun 04 2012 at 8:19am |
Gentlemen Something is very wrong with the above story. City Council approved the paving of the final leg of the bike path so where did the money go? Did they use the money for all the repairs that were needed? Here is the link to our other discussion http://middletownusa.com/forum/forum_posts.asp?TID=4048
|
|
409
Prominent MUSA Citizen
Joined: Mar 27 2009
Status: Offline
Points: 1014
|
Post Options
Thanks(0)
Quote Reply
Posted: Jun 04 2012 at 8:39am |
If I may, for easier access:
|
|
409
Prominent MUSA Citizen
Joined: Mar 27 2009
Status: Offline
Points: 1014
|
Post Options
Thanks(0)
Quote Reply
Posted: Jun 04 2012 at 8:50am |
City Manager Judy Gilleland said while quality of life amenities like the bike trail are an important aspect to the Middletown community, its’s not a top priority. “The bike path has been built over many, many years as grant funds became available. There has not been a guarantee that it would ever be complete but it’s a project we keep in the back of our minds if the funds become available,” she said. Gilleland said the city relies on funding it cannot use for essential city services, such as emergency services or maintenance of the streets. Only funds are earmarked for recreation trails or park-related activities would be used, she said. There are some initial discussions with regional organizations about funding options and resources. No city money was spent completing this recent leg of the trail. The bulk of the funding for this most recent portion — which cost $501,000 — came from an Energy Efficiency and Conservation Block Grant from the federal stimulus package. The remaining money came from the Middletown Community Foundation and the Miami Conservancy District.
This money should have been used for energy efficient lighting and the like to actually save us stakeholders some money!
|
|
VietVet
MUSA Council
Joined: May 15 2008
Status: Offline
Points: 7008
|
Post Options
Thanks(0)
Quote Reply
Posted: Jun 04 2012 at 11:11am |
Any story concerning city financing and the techniques used by Carolus and his "Amazing Kreskin" methods shouldn't surprise anyone. City money handling people have always practiced the old "slight of hand" routine when shuffling money from fund to fund, and are quite good at covering their tracks and using confusing language when asked to explain their procedures. The question of "what happened to the money" could be asked concerning the Street Repair Fund from the 80's as well as the questions being asked here. Citizens have never received a straightforward, logical, traceable answer. Need to have different people with an open agenda running the city to accomplish that and we all know that isn't going to happen soon.
|
|
Vivian Moon
MUSA Council
Joined: May 16 2008
Location: Middletown, Ohi
Status: Offline
Points: 4187
|
Post Options
Thanks(0)
Quote Reply
Posted: Jul 08 2012 at 6:37am |
Close to $1M needed to finish bike trail in Middletown
No city money spent on recent GMR Bike Trail leg; last portion could be costly.
By Michael D. Pitman, Staff Writer Updated 10:26 PM Saturday, June 2, 2012
MIDDLETOWN — The city will need close to $1 million in order to complete the final portion of the Great Miami River Bike Trail within the city. Officials with bike trail contractor Barry Brown Paving are checking off the final items on the punch list for the 1.2-mile stretch recently completed. The city now has about 9 miles of bike trails, and bikers and walkers can travel from Oxford State Road to close to North Breiel Boulevard Road. But the last nearly 2 miles of the trail — which will end at Baxter Drive in Franklin — will be costly. About $900,000 will be needed to construct that portion, but 55 percent of that cost is for about 1,000 feet of retaining walls, Rob Nichols, an engineer with the city’s Public Works and Utilities Department. “There’s not a whole lot of land and it would require a retaining wall,” said Nichols, “so it is more expensive.” Once that stretch is finished, bike riders will be able to travel to near Piqua on the trail. City Manager Judy Gilleland said while quality of life amenities like the bike trail are an important aspect to the Middletown community, its’s not a top priority. “The bike path has been built over many, many years as grant funds became available. There has not been a guarantee that it would ever be complete but it’s a project we keep in the back of our minds if the funds become available,” she said. Gilleland said the city relies on funding it cannot use for essential city services, such as emergency services or maintenance of the streets. Only funds are earmarked for recreation trails or park-related activities would be used, she said. There are some initial discussions with regional organizations about funding options and resources. No city money was spent completing this recent leg of the trail. The bulk of the funding for this most recent portion — which cost $501,000 — came from an Energy Efficiency and Conservation Block Grant from the federal stimulus package. The remaining money came from the Middletown Community Foundation and the Miami Conservancy District. The project was to be completed this past fall, Nichols said, but the schedule was compromised due to delays with the contractor and environmental red tape with approvals from the Ohio Department of Transportation.
|
|